NMI
The 10-11 character identifier for a connection point in the National Electricity Market. It is the key a customer must supply on Ausgrid's meter data request form, alongside the account holder name and postcode.
DNSP
The regulated operator of the poles, wires and substations that deliver electricity to end customers. Ausgrid is the DNSP for Sydney, the Central Coast and the Hunter. A DNSP is not a retailer and does not sell energy.
Zone substation
A substation stepping sub-transmission voltage down to distribution voltage. Ausgrid publishes 15-minute interval demand in MW for 180+ zone substations, one CSV per substation per financial year.
Interval data
Time-series electricity demand or consumption recorded at fixed intervals. Ausgrid publishes network interval demand at 15-minute resolution; customer interval meter data is supplied on request for up to 2 years of history in AEST.
DTAPR
The annual network planning report a distributor must publish. Ausgrid's Rule 5.13A reporting year runs May to May, and it commits to publishing 12 months of interval data in .csv within 30 business days of the report.
UHC
The headroom remaining on the network for additional load or additional generation at a given substation and voltage level in a given forecast year. Exposed as the fields available_capacity__load__at_n_ and available_capacity__generation_ on the Ausgrid_UHC_Data layers.
N-1
The contingency planning standard under which the network must still serve demand with one element out of service. Ausgrid's hosting capacity figures are stated at N-1, and the secondary layer additionally carries n_1_nameplate_capacity.
Feeder
A distribution circuit running from a substation into the network. Appears as the "object" value on the DTAPR line layer, with a name (e.g. "72F") and a voltage (e.g. "33kV").
Dual function asset
An asset performing both transmission and distribution functions, flagged by the dual_function field on the DTAPR line layer — a regulatory classification affecting which pricing and planning rules apply.
CDR
Australia's economy-wide data portability regime. Live in energy, but it designates electricity retailers as data holders with AEMO as gateway; distributors such as Ausgrid are not designated and Ausgrid does not appear in the public CDR energy data-holder register.
MSATS
AEMO's registry through which market participants exchange metering and connection point data. Distributors supply data into MSATS; this is the upstream path by which Ausgrid meter data reaches retailers, and it is not a public API.
DER
Customer-side generation and storage — rooftop solar, batteries, EV chargers — whose connection headroom is what the unallocated hosting capacity dataset describes.
Dynamic connection
A connection agreement under which export or import limits vary with network conditions. Ausgrid markets "real-time signals" for large customers under this heading but names no protocol and publishes no interface.